What is included in the options if the Commission decides to sue a contractor?

  1. Order for satisfactory completion

  2. Injunction against operations

  3. Revocation of license

  4. Increase in fees

The correct answer is: Order for satisfactory completion

In the scenario where the Commission decides to take legal action against a contractor, one potential outcome is the issuance of an order for satisfactory completion. This means that the contractor may be required to fulfill their contractual obligations satisfactorily, thereby ensuring that any work performed meets the necessary standards and is complete according to the terms of the agreement. This option underscores the regulatory authority's focus on maintaining quality and compliance within the construction industry. Such an order seeks to rectify any deficiencies or unsatisfactory work rather than immediately opting for punitive measures like revocation of a license or fines. It emphasizes the importance of fulfilling commitments and standards in the construction profession, reinforcing the need for contractors to comply with regulations and contract terms to protect consumer interests. In contrast, the other options, such as an injunction or license revocation, typically represent more severe repercussions that directly impact a contractor’s ability to operate, while an order for satisfactory completion aims to resolve issues while allowing the contractor the opportunity to correct them.